Tomorrow, April 12th, we will go back out to finish cutting the rest of the control joints in the middle section.
A project blog for the construction of Auburn University's new outdoor demonstration lab. The students in the McWhorter School of Building Science's Concrete Structures class are managing and executing all phases of the project.
Wednesday, April 11, 2012
Update: April 11th
Today we finished pouring the center strip of the slab. It went pretty smoothly after getting some practice from the first pour. The center strip did prove to be difficult due to its position, and we had to take precautions to keep from staining and scarring the other two previously poured sections.We also sprayed the cure and seal compound on the origional pour sections. Later that evening, several of us went back to cut the control joints in the outer two sections from the first pour. We cut the joints using a skill saw with a diamond blade.
Tuesday, April 10, 2012
Update: April 10th
Tuesday was day one of the concrete pour. The concrete truck arrived at 2:00, and we finished pouring the first section at 2:45. We then called for the second truck, and poured the next section at 3:15. The concrete truck driver was extremely easy to work with, and gave us pointers on how to be more efficient with screeding the concrete.
The entire day went smoothly, and each student had an opportunity to do every job involved in the pour; this included screeding, floating, troweling, brooming, and edging. Superintendents Branden Reagin and Michael Stroecker did a wonderful job delegating the work and remaining composed under pressure. They helped teach those with less experience how to work with the concrete. It was a very successful day. We will be pouring our last section tomorrow, April 11th.
![]() |
| Delivery ticket from concrete company. |
The entire day went smoothly, and each student had an opportunity to do every job involved in the pour; this included screeding, floating, troweling, brooming, and edging. Superintendents Branden Reagin and Michael Stroecker did a wonderful job delegating the work and remaining composed under pressure. They helped teach those with less experience how to work with the concrete. It was a very successful day. We will be pouring our last section tomorrow, April 11th.
Sunday, April 8, 2012
Update: April 8th
Friday, April 6, 2012
Week 1 Wrap-Up
Site Status as of Friday, April 6th:
Substantial progress was made this week.
Despite variable weather conditions, BSCI Construction Company managed to grade
the site, build and place the formwork and keyways, and lay out the
majority of the rebar cages.
Due to more thunderstorms, work yesterday and today
was cancelled. We will reconvene on Sunday afternoon to finish up the two-rebar
cages and the middle section of the sub grade.
We accomplished the goals we had set for the
week. If things work out accordingly, our first pour day is scheduled for the
afternoon of Tuesday, April 10th.
| The site before work commenced on Monday, April 2nd. |
| The site five days later, on Friday, April 6th. |
Tuesday, April 3, 2012
Day 2
Day 2 commenced with a brief meeting with Steve Williams,
our company president. He confirmed and approved the 50’ length of the slab
diagonal, and helped us figure out the logistics for efficiently using as many
people as we could on site.
The majority of the day was spent moving sand and
dirt to bring the location of the slab to grade. After figuring out where the
high spots and low spots were, we moved the sand with a shovel and wheelbarrow.
Our goal was to avoid moving sand more than necessary; although we leveled the
sub base, we still have about ½” to take off to satisfy the specified 4” slab.
Once the 3-10’ wide strips were screeded, we
worked on the interior formwork. The key component for the interior formwork
was the keyway. Superintendent Branden Reagin and his assistants glued and
nailed the quarter rounds onto a 2x4 and then set them.
A main difficulty here was the fact that we lacked a drill to fasten the form-stakes to the forms. We had to attach 5-100’ extension cords together to bring power out to the site so that we could operate a corded drill. The team only got this line of forms completed today.

Overall, today was much more efficient than yesterday. We assigned each person to either grade the slab or help with the formwork; this allocation of jobs kept work running proficiently at all times. The only reason we did not get more done was the sudden afternoon thunderstorm.
Weather permitting, we will continue this
process tomorrow. We will also begin putting the rebar in the slab.
Monday, April 2, 2012
Breaking Ground: First Official Workday
Today was the first formal workday for the AU Outdoor Demo Lab. There were about ten students on site at different times throughout the day. We focused on building the perimeter formwork, stalking the boards in, using a string to make a consistent elevation, and splicing the boards when necessary.
First, we set the elevations at the corners with string lines. Then, to build the perimeter formwork, we cut 2x4s into the correct lengths for each side of the exterior forms. The 40' sides were made of 3-12' boards, plus a 4'3" board on each side. The 30' sides were made of 10' boards; this will give the concrete truck ample room to be in the interior section on the day of the pour.