Tomorrow, April 12th, we will go back out to finish cutting the rest of the control joints in the middle section.
A project blog for the construction of Auburn University's new outdoor demonstration lab. The students in the McWhorter School of Building Science's Concrete Structures class are managing and executing all phases of the project.
Wednesday, April 11, 2012
Update: April 11th
Today we finished pouring the center strip of the slab. It went pretty smoothly after getting some practice from the first pour. The center strip did prove to be difficult due to its position, and we had to take precautions to keep from staining and scarring the other two previously poured sections.We also sprayed the cure and seal compound on the origional pour sections. Later that evening, several of us went back to cut the control joints in the outer two sections from the first pour. We cut the joints using a skill saw with a diamond blade.