Site Status as of Friday, April 6th:
Substantial progress was made this week.
Despite variable weather conditions, BSCI Construction Company managed to grade
the site, build and place the formwork and keyways, and lay out the
majority of the rebar cages.
Due to more thunderstorms, work yesterday and today
was cancelled. We will reconvene on Sunday afternoon to finish up the two-rebar
cages and the middle section of the sub grade.
We accomplished the goals we had set for the
week. If things work out accordingly, our first pour day is scheduled for the
afternoon of Tuesday, April 10th.
The site before work commenced on Monday, April 2nd. |
The site five days later, on Friday, April 6th. |