Friday, April 6, 2012

Week 1 Wrap-Up


Site Status as of Friday, April 6th:



Substantial progress was made this week. Despite variable weather conditions, BSCI Construction Company managed to grade the site, build and place the formwork and keyways, and lay out the majority of the rebar cages.

Due to more thunderstorms, work yesterday and today was cancelled. We will reconvene on Sunday afternoon to finish up the two-rebar cages and the middle section of the sub grade.

We accomplished the goals we had set for the week. If things work out accordingly, our first pour day is scheduled for the afternoon of Tuesday, April 10th



The site before work commenced on Monday, April 2nd. 



The site five days later, on Friday, April 6th.